FULIN-PROVISION, INSTALLATION AND COMMISSIONING OF FIRE FIGHTING CONTROL SYSTEM
According to requirement from Client – Fulin Plastic, TLC has provided the control panels for Fire Fighting pumps systems in plant.
The detailed scope of supplies consist of:
- Engineering works: drawings, specification, ITP.
- Providing complete control panels consisting of: 185KW inverter, MCCB, Contactor, Soft Starter, accessories in control panel.
- Providing complete set of Fire Fighting pump-160KW.
- Installing whole system.
- Testing and commissioning system.
- Handing over system to Client.
Building panel in workshop-01
Building panel in workshop-02
Building panel in workshop-03
Building panel in workshop-04
Building panel in workshop-05
Delivering panels to plant-01
Delivering panels to plant-02
Delivering panels to plant-03
Installing panels at position-01
Installing panels at position-02
Installing panels at position-03
Installing panels at position-04
Installing panels at position-05
Performing Testing&Commissioning works-01
Performing Testing&Commissioning works-02
Performing Testing&Commissioning works-03
Performing Testing&Commissioning works-04
Performing Testing&Commissioning works-05
Related news
MECHANICAL SERVICE FOR MEGA STEEL PROJECT
MECHANICAL SERVICE FOR MEGA STEEL...
MINING – EC&I PROJECT
TLC is serving An International Project Team - The Mining Project.....
RENOVATION NBJ PROJECT FOR PAPER PLANT
TLC just completed NBJ project for Paper Plant in Collaboration Biz Model with OEM contractor ...
SPEED UP PROGRESS FOR C&I DCS OF PAPER MACHINE
The Paper Machine is going to Commissioning stage, TLC is speeding up the progress of installation...
THE COGEN 30MW PROJECT IN ACCELERATION STAGE
After the Covid 19 4th booming in South of Vietnam, TLC accelerating the Co-Generation 30MW...
LUB OIL BLENDING PLANT
TLC is executing the project of “LUB OIL BLENDING PLANT”. The scope of works are:...
+84(0)91 587 6679