INSTALLATION OF 500KV CTS FOR 500KV POWER STATION OF COMBINED CYCLE POWER PLAN (CCPP)

TLC got the contract of provision of materials and installation of foundation, steel structure, 500KV CT for 500KV power station of Combined Cycle Power Plan (CCPP).

The detailed scope of works consists of:

  • Provision of concrete foundation
  • Provision of steel structure
  • Installation of 500KV CTs
  • Installation and termination  of power and control, instrument cables
  • Testing and commissioning system.

Reference pictures

500KV CT project Kick Off Meeting

TLC daily Tool Box Meeting-01

TLC daily Tool Box Meeting-02

TLC daily Tool Box Meeting-03

TLC daily Tool Box Meeting-04

TLC daily Tool Box Meeting-05

Surveying and positioning activities for foundation works- 01

Surveying and positioning activities for foundation works-02

Surveying and positioning activities for foundation works-03

Surveying and positioning activities for foundation works-04

Surveying and positioning activities for foundation works-05

Fabrication of steel structures at workshop-01

Fabrication of steel structures at workshop-02

Fabrication of steel structures at workshop-03

Fabrication of steel structures at workshop-04

Fabrication of steel structures at workshop-05

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-01

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-02

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-03

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-04

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-05

Trial assembling structures at workshop after completed Hot Dip Galvanized statge-06

Factory Acceptance Inspection (FAI) at workshop before delivering to construction site-01

Factory Acceptance Inspection (FAI) at workshop before delivering to construction site-02

Factory Acceptance Inspection (FAI) at workshop before delivering to construction site-03

Delivering steel structures to job site-01

Delivering steel structures to job site-02

Delivering steel structures to job site-03

Delivering steel structures to job site-04

 

Related news

TLC IN PAPER PLANT PROJECTS

TLC IN PAPER PLANT...

TLC IN POWER PLANT PROJECTS

TLC IN POWER PLANT PROJECTS

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

MECHANICAL SERVICE FOR MEGA STEEL PROJECT

MECHANICAL SERVICE FOR MEGA STEEL...

MINING – EC&I PROJECT

TLC is serving An International Project Team - The Mining Project.....

RENOVATION NBJ PROJECT FOR PAPER PLANT

TLC just completed NBJ project for Paper Plant in Collaboration Biz Model with OEM contractor ...

CUSTOMERS-PROJECT

zalo