SAIGON PAPER

Project: Saigon Paper
Scope of works:
Upgrading the systems of Power, Drives, Control of PM4, PM5, PM6 production lines: provision, installation, testing and commissioning the panels, cable raceway, cables
Schedule:
2 weeks for each lines, working continuously before, during, after Tet mau Tuat 2018

The Engineers, Workers of TLC have closely cooperated with Experts, Engineers of Saigon Paper, worked hard to complete the works of provision, installation, testing and commissioning all equipment, materials and set production lines in operation successfully in accordance with desired schedules.

TLC team mobilizing for works.

HSE conduction-01

HSE conduction-02

HSE conduction-03

Tool Box Meeting-01

Tool Box Meeting-02

Tool Box Meeting-03

Tool Box Meeting-04

TLC engineers at working place

 

 

Related news

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

MECHANICAL SERVICE FOR MEGA STEEL PROJECT

MECHANICAL SERVICE FOR MEGA STEEL...

MINING – EC&I PROJECT

TLC is serving An International Project Team - The Mining Project.....

RENOVATION NBJ PROJECT FOR PAPER PLANT

TLC just completed NBJ project for Paper Plant in Collaboration Biz Model with OEM contractor ...

SPEED UP PROGRESS FOR C&I DCS OF PAPER MACHINE

The Paper Machine is going to Commissioning stage, TLC is speeding up the progress of installation...

THE COGEN 30MW PROJECT IN ACCELERATION STAGE

After the Covid 19 4th booming in South of Vietnam, TLC accelerating the Co-Generation 30MW...

CUSTOMERS-PROJECT

zalo