CHANGING NEW 24KV SIEMENS CB FOR STEEL PLANT

"TLC has completed the job of Provision and Replacement of new 24KV Siemens CB for Steel Plant. TLC has perform the replacement works and testing and commissioning under the supervision of Japanese supervisors. TLC has completed all the works and energized the Switchgear on time as expectation of Client"

Testing and Commissioning Siemens CB-01

Testing and Commissioning Siemens CB-02

Changing 24KV Siemens CB-01

Changing 24KV Siemens CB-02

Changing 24KV Siemens CB-03

Changing 24KV Siemens CB-04

Changing 24KV Siemens CB-05

Changing 24KV Siemens CB-06

 

 

Related news

TLC IN PAPER PLANT PROJECTS

TLC IN PAPER PLANT...

TLC IN POWER PLANT PROJECTS

TLC IN POWER PLANT PROJECTS

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

REVAMPING THE DRIVE SYSTEMS FOR PAPER MACHINE

MECHANICAL SERVICE FOR MEGA STEEL PROJECT

MECHANICAL SERVICE FOR MEGA STEEL...

MINING – EC&I PROJECT

TLC is serving An International Project Team - The Mining Project.....

RENOVATION NBJ PROJECT FOR PAPER PLANT

TLC just completed NBJ project for Paper Plant in Collaboration Biz Model with OEM contractor ...

CUSTOMERS-PROJECT

zalo