TLC-TTC2 SOLAR FARM PROJECT IN SPEEDY STAGE
TTC2 Solar Farm project was in speedy stage. Owner and EPC contractor JGC decided energizing in the end of March 2019.
TLC and other contractors paid a lot of efforts together executing the installation, Testing and Commissioning works. TLC has worked through Tet Ky Hoi festival in order to reach the desired schedule for 22/110KV-61MVA substation and AC, DC, utility systems.
The working activities performed in dayshift, nightshift with highest drastic spirit.
Some below pictures recorded activities of TLC in this stage:
TTC Solar Farm project overview
.png)




Daily morning TBM





Going to jobsite for works


Installing equipment in 22/110KV-63MVA substation


Installing equipement in CCR building in substation

Installing equipement in CCR building in substation


Installing PCS on foundation




Pulling AC cables


Pulling DC cables




Cable termination works





Testing and Commissioning



Award and recorgnization for HSSE performance in project



Joys in working




Beautiful colors of jobsite

Comradeship of TLC brothers – Together we go further

Related news
+84(0)91 587 6679
CUSTOMERS-PROJECT



(1).png)



.jpg)



.jpg)
.jpg)
.jpg)

.jpg)

.jpg)
.jpg)
.jpg)


.jpg)


.png)

