TLC-TTC2 SOLAR FARM PROJECT IN SPEEDY STAGE

TTC2 Solar Farm project was in speedy stage. Owner and EPC contractor JGC decided energizing in the end of March 2019.

TLC and other contractors paid a lot of efforts together executing the installation, Testing and Commissioning works. TLC has worked through Tet Ky Hoi festival in order to reach the desired schedule for 22/110KV-61MVA substation and AC, DC, utility systems.

The working activities performed in dayshift, nightshift with highest drastic spirit.

Some below pictures recorded activities of TLC in this stage:

TTC Solar Farm project overview

Daily morning TBM

Going to jobsite for works

Installing equipment in 22/110KV-63MVA substation

Installing equipement in CCR building in substation

Installing equipement in CCR building in substation

Installing PCS on foundation

Pulling AC cables

Pulling DC cables

Cable termination works

Testing and Commissioning

Award and recorgnization for HSSE performance in project

Joys in working

Beautiful colors of jobsite

Comradeship of TLC brothers – Together we go further

Related news

CUSTOMERS-PROJECT

zalo