INSTALLATION OF 22/110KV-63MVA SUB-STATION

TLC INSTALLS THE 22/110KV-63MVA SUB-STATION

TLC is installing the Step-up transformer sub-station 22/110KV-63MVA for TTC2 Solar power plant.

The scope of work consists of:

  • Installation of step-up transformer 22/110KV-63MVA.
  • Installation of primary-secondary component in switch yard.
  • Installation of primary-secondary power panels and control panels in control building.
  • Oil filtering works.
  • Testing and Commissioning the substation.

Below pictures are taken during sub-station installation progress:

Istallation of Primary-Secondary equipments in switch yard: CB, DS, PT, CT, SA…

Installation of MV, LV, Control panels in Control Building

Overview of 22/110KV-2x63MVA sub-station

Installation of transformer 22/110KV-63MVA

The preparation and oil filtering in progress

Istallation of Promary-Secondary equipments in switch yard

 

 