TLC-TTC2 SOLAR FARM PROJECT IN SPEEDY STAGE

TTC2 Solar Farm project was in speedy stage. Owner and EPC contractor JGC decided energizing in the end of March 2019.

TLC and other contractors paid a lot of efforts together executing the installation, Testing and Commissioning works. TLC has worked through Tet Ky Hoi festival in order to reach the desired schedule for 22/110KV-61MVA substation and AC, DC, utility systems.

The working activities performed in dayshift, nightshift with highest drastic spirit.

Some below pictures recorded activities of TLC in this stage:

TTC Solar Farm project overview

Daily morning TBM

Going to jobsite for works

Installing equipment in 22/110KV-63MVA substation

Installing equipement in CCR building in substation

Installing equipement in CCR building in substation

Installing PCS on foundation

Pulling AC cables

Pulling DC cables

Cable termination works

Testing and Commissioning

Award and recorgnization for HSSE performance in project

Joys in working

Beautiful colors of jobsite

Comradeship of TLC brothers – Together we go further

Related news

PROJECT EXECUTION FOR NEW INDUSTRIAL PROJECT

Starting 2020, we contracted with Customer for project execution of new project in industrial field...

PROVIDING ELECTRICAL SYSTEMS FOR WOOD FACTORY

Wood industry is a booming business in Vietnam, TLC has stepped into this business, TLC contract...

PROVIDING, REPLACING, TESTING, ENERGIZING THE...

In 3/2020, TLC had completed the contract of providing, replacing testing, energiging the 22KV CB...

FIXING OIL LEAKAGES FOR POWER TRANSFORMERS

In February 2020 TLC had com[leted the service of “Fixing oil leakages” for power...

REPLACEMENT OF HUB FOR THE TECHNOLOGICAL FAN...

In February 2020, TLC had completed the service of replacement of hub for the technological fan...

CUSTOMERS-PROJECT