Vina Kraft Paper Company

The Owner: SCG Paper Group with capacity of 220,000 tons/year.

Tuyen Lam scope of works:

  • 2008-2009: installation of DCS systems, electrification systems for ESP, auxiliary systems during construction phase (cubicles, cable systems…)
  • 2010-2012: several jobs of modification, extension. Maintenance for all HVAC systems. Maintenance for MV, LV Switchgear.
  • 2009- 2013: Maintenance for MV, LV Switchgear. Installation of electrification systems for Fenton, Debottleneck&Size Press, and other several  projects.
  • 2016: Local contractor for provision of cable raceway systems and installation, testing and commissioning the electrification systems with Siemens Group .

Cable connection in Electric Panel

Cable connection in LV MCC

Cable connections for motor

Cable termination in MCC

Cogen complex in construction

ETP in commissioning stage

Installation of Electrical systems for pumps at Chemical Plant

Installing the control valves

Installing the field transmiter

Installing the Pneumatic Systems

Moving 6.6KV motor

Paper on reel

Relocation of 6.6KV motors

T&C works for motor

 

 

Related news

CJFM-EC&I PROJECT

TLC got the contract of provision of Electrical, control and instrument systems for new plant...

FULIN-PROVISION, INSTALLATION AND COMMISSIONING...

TLC has provided the control panels for Fire Fighting pumps systems in plant...

PHU MY 3 CCPP-OUTAGE 2018

Discussion with Siemens specialists before executing at job...

CUSTOMERS-PROJECT