TTC2 SOLAR FARM 50MW PROJECT

TTC2 SOLAR FARM 50MW-UPDATED 10.01.2019

TLC-SANKO is is progress of installation of 22/110KV-63MVA step-up power transformer, installation of components of 22/110KV substation, pulling and terminating Medium Voltage cables, Low Voltage cables.

Below pictures are taken during site executing activities:

TLC site facilities: Office-Storage-Workshop at the main project management offices

TLC Office at TTC2 job site. TLC used Solar Power for office usage.

TLC staff at job site daily morning

TLC equipped the roofs at job site for staff taking rest

Cable pulling activities

Preparing and protecting cables at job site

 

Installation of transformer station 22 / 110KV-63MVA

Thermo-chemical welds for grounding system at jobsite

TLC Site facilities: Office-Storage-Workshop

TLC equipment at site

TLC Manpower: Engineers, management-Supervisors-Workers…

HSE Training

Daily Tool Box Meeting-TBM

Discussion before starting the works at site

Sanko-Japanese specialist at site for technical supervision

Loading and transporting cables to jobsite

Preparing cables for pulling works

Cable pulling

Sand filling in cable trench

 

Related news

MINING – EC&I PROJECT

TLC is serving An International Project Team - The Mining Project.....

RENOVATION NBJ PROJECT FOR PAPER PLANT

TLC just completed NBJ project for Paper Plant in Collaboration Biz Model with OEM contractor ...

SPEED UP PROGRESS FOR C&I DCS OF PAPER MACHINE

The Paper Machine is going to Commissioning stage, TLC is speeding up the progress of installation...

THE COGEN 30MW PROJECT IN ACCELERATION STAGE

After the Covid 19 4th booming in South of Vietnam, TLC accelerating the Co-Generation 30MW...

LUB OIL BLENDING PLANT

TLC is executing the project of “LUB OIL BLENDING PLANT”. The scope of works are:...

SUPPLY AND SERVICES FOR STEEL PLANT

TLC  is contractor for providing the 22KV Circuit Breaker panel and service of installation,...

CUSTOMERS-PROJECT

zalo