SAIGON PAPER

Project: Saigon Paper
Scope of works:
Upgrading the systems of Power, Drives, Control of PM4, PM5, PM6 production lines: provision, installation, testing and commissioning the panels, cable raceway, cables
Schedule:
2 weeks for each lines, working continuously before, during, after Tet mau Tuat 2018

The Engineers, Workers of TLC have closely cooperated with Experts, Engineers of Saigon Paper, worked hard to complete the works of provision, installation, testing and commissioning all equipment, materials and set production lines in operation successfully in accordance with desired schedules.

TLC team mobilizing for works.

HSE conduction-01

HSE conduction-02

HSE conduction-03

Tool Box Meeting-01

Tool Box Meeting-02

Tool Box Meeting-03

Tool Box Meeting-04

TLC engineers at working place

 

 

Related news

CJFM-EC&I PROJECT

TLC got the contract of provision of Electrical, control and instrument systems for new plant...

FULIN-PROVISION, INSTALLATION AND COMMISSIONING...

TLC has provided the control panels for Fire Fighting pumps systems in plant...

PHU MY 3 CCPP-OUTAGE 2018

Discussion with Siemens specialists before executing at job...

CUSTOMERS-PROJECT